大容量交直流船舶電站試驗(yàn)工裝配置方案研究

打開文本圖片集
中圖分類號:U665.12 文獻(xiàn)標(biāo)志碼:A
Research on the Configuration Scheme of Testing Equipment forHigh-CapacityAC/DC ShipboardPower Stations
YANG Yanan(Hudong-Zhonghua Shipbuilding(Group) Co.,Ltd.,Shanghai20o129,China)
Abstract: This paper addresses the issue that domestic shipyards lack experience in the configuration of mooring test equipment for AC/DC power stations with relevant capacity levels, especially regarding the first applicationoflarge-capacity medium-voltage DC integrated power systems on vessels.Based on thedemand analysis for the mooring test of a ship's large-capacityAC/DC power station,a comprehensive configurationscheme for the power station's test load,cables,andcable trays is proposed.This solution resolves the chalengesof providing the necessary test conditions for high-capacityAC/DC shipboard power stations and offers areference for the application of similar systems on other vessels.
Key words: high-capacity AC/DC power station; testing equipment; configuration scheme
1 引言
隨著我國綜合電力系統(tǒng)在船舶領(lǐng)域的快速發(fā)展,第二代綜合電力系統(tǒng)—中壓直流綜合電力系統(tǒng)由研發(fā)階段開始進(jìn)入實(shí)船應(yīng)用階段。(剩余4501字)